The purpose of this project is to resurface State Road (S.R.) 50 (West Colonial Drive) from Tampa Avenue/Country Lane to S.R. 500/U.S. 441 (Orange Blossom Trail).

Additional improvements include drainage upgrades, curb and gutter work, sidewalk removal and reconstruction, signing and pavement markings, and traffic signal work.

Lane Closures
  • Sunday, January 19th, 2020 to Saturday, January 25th, 2020

    8:30 p.m. to 6:30 a.m.
    Eastbound and westbound outside lane closure from Tampa Avenue to US 441 for drainage and concrete work.

  • Sunday, January 26th, 2020 to Saturday, February 1st, 2020

    8:30 p.m. to 6:30 a.m.
    Eastbound and westbound outside lane closure from Tampa Avenue to US 441 for drainage and concrete work.