This project will resurface all lanes of I-95, including on and off ramps from north of Palm Coast Parkway to the St. Johns County line. This project goes with 438003-1, extending the project limits in Flagler County from the Volusia County line to the St. Johns County line.

Work also will include guardrail, shoulder improvements, ITS, pier protection and emergency U-turns.

Lane Closures
  • Sunday, August 18th, 2019 to Saturday, August 24th, 2019

    Sunday - Thursday, 5 p.m. - 9 p.m. single lane closures, and 9 p.m. - 7 a.m., double lane closures on northbound I-95 north of Palm Coast Parkway to the St. Johns County line.