EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

This project has been completed and is only available for historical reference.
Project Details
Work Type: Resurfacing
Phase: Completed
Length: .701 miles
County:
Road:
Project Start: Early 2019
Est. Completion: Spring 2019
About

The purpose of this project is to rehabilitate the asphalt pavement by milling and resurfacing the travel lanes and shoulders of State Road (S.R.) 44A from East New York Avenue (S.R. 44) to east of Grimm Lane. A detectable warning surface will be added to the sidewalk terminal at the cul-de-sac, the existing signs will be evaluated and updated as needed and the existing traffic signal loops will be replaced.