The purpose of this project is to mill and resurface all travel lanes on State Road (S.R.) 406 (Garden Street) from Petty Circle to S.R. 5/U.S. 1 Northbound (Washington Ave). Bicycle lanes will be added through a restriping process. Improvements will also be made to the curb and gutter, sidewalks, pedestrian ramps, and traffic separators.

This project is affiliated with project numbers: 432399-1-52-01 and 436187-3-52-01

Lane Closures
  • Friday, November 16th, 2018 to Sunday, November 25th, 2018

    Daytime lane closures for roadwork

    Sunday-Tuesday 7 p.m.-7:30 a.m. single outside lane closure eastbound and westbound on S.R. 406 (Garden Street) for road work

    Monday-Tuesday, 7 a.m.-5 p.m. double lane closures eastbound and westbound on S.R. 406 (Max Brewer Bridge) for roadwork