This project consist of milling and resurfacing, drainage improvements, traffic signals, signing and pavement markings and miscellaneous improvements.
Lane Closures
  • Monday, March 25th, 2019 to Friday, March 29th, 2019

    NORTHBOUND

    The Contractor will be widening the existing roadway, pouring concrete sidewalk and curb and gutter on northbound U.S. 441 from Jones Avenue to Wadsworth Road.

     

    The work will begin Monday, March 25 thru Friday, March 29 from 4 a.m. to 4 p.m.

     

    SOUTHBOUND 

    The Contractor will be widening the existing roadway, pouring concrete sidewalk, curb and gutter and installing pipe on southbound U.S. 441 from Jones Avenue to Wadsworth Road.

     

    The work will begin Monday, March 25 thru Friday, March 29 from 9 a.m. to 6 p.m.

  • Monday, April 1st, 2019 to Friday, April 5th, 2019

    NORTHBOUND

    The Contractor will be widening the existing roadway, pouring concrete sidewalk and curb and gutter on northbound U.S. 441 from Jones Avenue to Wadsworth Road.

     

    The work will begin Monday, April 1 thru Friday, April 5 from 4 a.m. to 4 p.m.

     

    SOUTHBOUND 

    The Contractor will be widening the existing roadway, pouring concrete sidewalk, curb and gutter and installing pipe on southbound U.S. 441 from Jones Avenue to Wadsworth Road.

     

    The work will begin Monday, April 1 thru Friday, April 5 from 9 a.m. to 6 p.m.

     