Project Details
Work Type: Add Turn Lane
Phase: Construction
Length: .069 miles
City:
County:
Road:
Construction Cost: $2.04 Million
Project Start: Summer 2020
Est. Completion: Early 2021
About
This work on this project will modify the existing turn lane on westbound State Road (S.R.) 44 at Palmetto Street by extending its length back to Live Oak Street and restriping it to allow through traffic and right-turn traffic.

This project goes with FIN # 442499-1, which will include an Adaptive Signal Control System on S.R. 44 from Airport Road to 3rd Avenue and from Palmetto Street to Live Oak Street.