This project has been completed and is only available for historical reference.
Project Details
Work Type: Add Turn Lane
Phase: Completed
Length: 0.359 miles
City:
County:
Road:
Construction Cost: $1.1 Million
Project Start: Spring 2020
Est. Completion: Late 2020
About

Improvements consist of widening the roadway to add turn lanes along State Road (S.R.) 405 (Columbia Boulevard) in Titusville. Left turn lanes will be added to turn left onto northbound Sisson Road.  he project will also include widening for bike lanes, milling and resurfacing, drainage improvements and the installation of new traffic signals. 