This project has been completed and is only available for historical reference.
Project Details
Work Type: Add Turn Lane
Phase: Completed
Length: 0.216 miles
County:
Road:
Construction Cost: $1.2 Million
Project Start: Early 2020
Est. Completion: Fall 2020
About

This project will add a right turn lane for southbound County Road (C.R.) 25A (NW Gainesville Road) to westbound State Road (S.R.) 326 (NW 77th Street). In addition, the project will construct a new right turn lane from westbound S.R. 326 to northbound C.R. 25A.

Contact Information
Contractor
Heavy Civil, Inc.