Project Details
Work Type: New Traffic Signal
Phase: Completed
Length: 0.026 miles
City:
County:
Road:
Construction Cost: $1.22 Million
Project Start: Early 2020
Est. Completion: Fall 2020
About

The purpose of this project is to provide traffic signal upgrades for the intersection of State Road (S.R.) A1A (Atlantic Avenue) and Cardinal Drive. This project will also provide pedestrian lighting and Americans with Disabilities Act (ADA) improvements.

This project goes with FIN# 438017-1, which will provide a mast arm signal at Harvard Drive and S.R. A1A.

Contact Information
Contractor
Chinchor Electric, Inc.