Project Details
Work Type: Lighting
Phase: Completed
Length: 12.345 miles
City:
County:
Road:
Construction Cost: $322,056
Project Start: Summer 2017
Est. Completion: Fall 2018
About

As part of the updates to the latest Plans Preparation Manual (PPM), the Florida Department of Transportation (FDOT) added a policy to light all interchanges on the Interstate system by Fiscal Year 2019, whether they meet the justification warrants or not. This project will provide complete interchange lighting design for three interchanges: Interstate 95 (I-95) / State Road (S.R.) 9 at Wickham Road, I-95 / S.R. 9 at S.R. 520, and I-95 / S.R. 9 at S.R. 524. The project is expected to improve nighttime visibility for the traveling public.

 

Contact Information
Contractor
Chinchor Electric, Inc.
Communications Team
Michelle Simmons
(305) 772-8155
michelle.simmons@exp.com