Project Details
Work Type: Widening
Phase: Construction
Length: 4.157 miles
City:
County:
Road:
Construction Cost: $45 Million
Project Start: Summer 2020
Est. Completion: Spring 2024
About

This is a project to widen U.S. 441/U.S. 27/State Road (S.R.) 500 from four to six lanes between Lake Ella Road and Avenida Central. Both northbound and southbound U.S. 441 will be expanded from two to three lanes, and bicycle lanes and sidewalks will be added along the length of the project. The FDOT will also do drainage work, add signage, make lighting upgrades, make median access changes and improve the aesthetics of the roadway with new landscaping.

A key aspect of the project was the removal of U.S. 441 bridges over County Road (C.R.) 25 which will allow for a new, at-grade intersection to be built at that location. C.R. 25 will connect with U.S. 441 on the east side of the highway via a signalized intersection and end as a cul-de-sac on the west side.

Contact Information
Contractor
Southland Construction, Inc.
Communications Team
Matt Young
(352) 326-7744 / (352) 620-3020
MattA.Young@dot.state.fl.us
For Media Inquiries Only
FDOT-D5Comm@dot.state.fl.us
Lane Closures
  • Sunday, April 21, through Friday, April 26, from 8 p.m. to 7 a.m.: Motorists should expect northbound and southbound lane closures on U.S. 441 from Lake Ella Road to Avenida Central for paving operations. Please reduce your speed, alertly merge into the open lane and cautiously pass through the work zone.