Volusia County- Earlier today, Feb. 8, crews completed work needed to address a depression that had formed underground near the roadway along Saxon Boulevard in Deltona. With work complete, the right lane of westbound Saxon Boulevard, near the I-4 overpass, has been reopened.

 

Work began Feb. 4, and was anticipated to take up to 10 days. This work included a grouting operation, where a fluid concrete is injected to create a stable base underground. Crews completed repairs in five days and pumped 130 cubic yards of grout underground. Total cost of the repair was approximately $150,000.

Drivers along Saxon Boulevard in Deltona will see continue to see activity in the area for the on-going resurfacing project. Paving work on this project is scheduled to occur sometime next week.

In construction zones and always, please avoid distractions while driving. Stay alert. Put the phone down. It can wait.