Bridge Construction on SR 33 in Lake County near City of Clermont [433860-1] View Project
  • Monday, February 25th, 2019 to Saturday, January 18th, 2020

    At this time, construction to replace the Green Swamp bridge on State Road (S.R.) 33 is tentatively scheduled to begin the week of January 6, 2020. 

    To aid mobility and commerce, a temporary bridge is being built along S.R. 33, adjacent to the current bridge. This allows traffic to flow during the demolition and reconstruction of the mainline bridge. The temporary bridge is one lane only. Special lighting and signals are being installed for both northbound and southbound traffic to allow drivers traveling each direction to alternate crossing the bridge.

  • Monday, January 13th, 2020 to Saturday, January 18th, 2020

    7 a.m. to 5 p.m.
    Single alternating lane closures with flaggers from south of County Road 561 to north of County Road 474 for land clearing and installing barrier wall. Please expect delays when traveling in this area.