Friday, October 4th, 2019 to Thursday, January 30th, 2020
Full Closure of Matanzas Woods Parkway at U.S. 1 starting October 28, 2019, closure is expected to last around 4 months.
Sunday- Saturday, single outside lane closures NB and SB U.S. 1 near Matanzas Wood Parkway to construct roundabout.
-
Thursday, November 21st, 2019 to Friday, January 31st, 2020
Starting Monday, Nov. 18, drivers traveling both northbound and southbound on U.S. 1 will now utilize the newly constructed roundabout, as follows:
- Northbound U.S. 1 traffic will continue north on U.S. 1 and can use either lane.
- Southbound U.S. 1 traffic will travel down the existing lane of the southbound roadway and enter the roundabout to continue south on U.S. 1.
- Northbound U.S. 1 traffic will use the right lane to access Old Dixie Highway or County Road (C.R.) 325.
- Southbound U.S. 1 traffic wishing to access Old Dixie Highway or C. R. 325 will travel through the roundabout to access the roadways.
This new traffic pattern will allow the contractor to complete the southbound U.S. 1 bypass lanes, and the southbound traffic separator at the roundabout. For more information about modern roundabouts please visit fdot.tips/roundabout
-
Wednesday, December 4th, 2019 to Tuesday, December 31st, 2019
Northbound S.R. A1A traffic will be shifted onto the newly constructed southbound roadway between South 23rd and South 7th Street in Flagler Beach beginning Thursday, Dec. 5.
The Southbound S.R. A1A detour is still in effect. All southbound traffic is detoured onto South Central Avenue from South 7th Street to South 23rd Street. The detour will be in place until the completion of S.R. A1A between South 22nd Street and South 9th Street. Access to all businesses and residences will be maintained.
-
Friday, December 6th, 2019 to Saturday, December 21st, 2019
Sunday- Saturday, 9 p.m. - 7 a.m., double lane closures on NB and SB I-95 north of Palm Coast Parkway to the St. Johns County line.