Project Details
Work Type: Construction Work
Phase: Completed
Length: .981 miles
City:
County:
Road:
Project Start: Early 2019
Est. Completion: Early 2020
About
This project involves permanent repairs by repairing and revetment of the dunes in Flagler Beach. Work involves fortifying the dune with additional sand and vegetation.

This construction is a result of damage caused by Hurricane Matthew and is one of three segments of S.R. A1A in Flagler County receiving repairs. The other segments fall under project numbers 440557-6 and 440557-7. All three segments are being constructed under one contract at a combined total cost of about $22.4 million.

As of July 31, 2019, work on this segment is substantially complete.

Contact Information
Contractor
Superior Construction Company Southeast, LLC
Communications Team
Britney Jones
(386) 740-3566
Britney.Jones@dot.state.fl.us