This project has been completed and is only available for historical reference.
Project Details
Work Type: Bike Path
Phase: Completed
Length: 1.098 miles
City:
County:
Road:
Construction Cost: $661,000
Project Start: Spring 2018
Est. Completion: Summer 2018
About
This project constructs a new shared use path along the east side of State Road (S.R.) 15/U.S. 17 from north of Washington Avenue to Palmetto Avenue in Pierson. The project includes the 1-mile path with associated drainage improvements. This project's design and construction are being funded through the Florida Department of Transportation's SUN Trail Network Program.