This project consists of milling and resurfacing the existing pavement within the project limits.  New sidewalks will be constructed where needed to provide continuous pedestrian access within the project limits.  Minor widening and restriping will be accomplished to provide bicycle keyhole lanes within the rural limits.  Within the urban limits, bike lanes will be provided by restriping and eliminating on-street parking.

Lane Closures
  • Sunday, December 9th, 2018 to Friday, December 21st, 2018

    The Contractor will be closing one lane at a time on northbound and southbound US 441 between the 429 Connector Road to West of Lake Doe Blvd. The Contractor will be paving.

    • Sunday, December 9 thru Friday December 14
    • From 7 p.m. to 7 a.m.

     

    • Sunday, December 16 thru Friday December 21
    • From 7 p.m. to 7 a.m.

     

  • Monday, December 10th, 2018 to Friday, December 21st, 2018

    The Contractor will be closing one lane at a time on northbound and southbound US 441 between the 429 Connector Road to West of Lake Doe Blvd. The Contractor will be excavating and pouring concrete

    • Monday, December 10 thru Friday December 14
    • Southbound - From 9:30 a.m. to 7 p.m.

     

    • Monday, December 17 thru Friday December 21
    • Northbound - From 7 a.m. to 3 p.m.

     