This project has been completed and is only available for historical reference.
Project Details
Work Type: Drainage Construction
Phase: Completed
Length: .090 miles
City:
County:
Road:
Construction Cost: $1.4 Million
Project Start: Fall 2018
Est. Completion: Spring 2019
About

This project will add curb inlets and replace existing storm drain pipe on S.R. 600/U.S. 92/International Speedway Boulevard from Emmet Street to North Charles Street, and on North Charles Street from International Speedway Boulevard to north of West Street.

 

Other improvements include milling and resurfacing of International Speedway Boulevard from Helme Place to South Charles Street, curb and gutter, sidewalks, pavement markings and other incidental construction.

Contact Information
Contractor
GPS Civil Construction, Inc.