This project has been completed and is only available for historical reference.
Project Details
Work Type: Drainage Construction
Phase: Completed
Length: .289 miles
City:
County:
Road:
Construction Cost: $1.68 Million
Project Start: Early 2018
Est. Completion: Late 2018
About
The goal of this project is to resolve the flooding issue on State Road 25/500/U.S. 27/301/441 (South Pine Avenue) by replacing the existing storm sewer pipe and drainage structures from Southeast 10th Avenue to Southeast 31st Street. Work will also include milling and resurfacing, roadway widening, reconstructing curb and gutters, installing sidewalks, upgrading signing and pavement markings, and updating underground components of lighting and traffic signals.
Contact Information
Contractor
Commercial Industrial Corp.