Project Details
Work Type: Lighting
Phase: Completed
Length: 2.940 miles
City:
County:
Road:
Construction Cost: $2.76 Million
Project Start: Fall 2016
Est. Completion: Early 2018
About
As part of the updates to the latest Plans Preparation Manual (PPM), the Florida Department of Transportation (FDOT) added a policy to light all interchanges on the Interstate system by Fiscal Year 2019.

This project will provide complete interchange lighting design for two interchanges: I-95 (SR 9) at Pineda Causeway and I-95 (SR 9) at Fiske Boulevard. The project is expected to improve nighttime visibility for the traveling public.