This project consists of milling and resurfacing, widening turn lanes, base work, shoulder treatment, drainage improvements, curb and gutter, sidewalks, signing and pavement markings, guardrail, signalization and ITS on State Road (S.R.) 25 (U.S. 27) from just west of County Road (C.R.) 561 (Lake Minneola Shores/Southern Breeze Drive) to 400 feet north of O'Brien Road. 
Lane Closures
  • Monday, August 13th, 2018 to Saturday, August 18th, 2018

    Southbound and northbound single lane closures anytime for signal work, drainage work and roadway widening.

  • Monday, August 20th, 2018 to Saturday, August 25th, 2018

    7:30 a.m. to 6 p.m.
    10 p.m. to 6 a.m.
    Southbound and northbound single lane closures for signal work, drainage work and roadway widening.