Project Details
Work Type: Safety Project
Phase: Completed
Length: 3.105 miles
County:
Road:
Construction Cost: $5.83 Million
Project Start: Spring 2017
Est. Completion: Fall 2018
About
This project will construct new sidewalks along the north and south sides of S.R. 520 and will tie into the existing sidewalk near Aurora Road.

This project also goes with a resurfacing project (432443-1) along SR 520 and will be constructed at the same time.