Project Details
Work Type: Widening
Phase: Completed
Length: 1.370 miles
City:
County:
Road:
Construction Cost: $13.44 Million
Project Start: Fall 2015
Est. Completion: Late 2018
About

This project includes pavement widening, median access changes, drainage improvements, curb and gutter, sidewalk, milling and resurfacing, pavement markings and signing, signalization, and water and sanitary sewer construction on State Road (S.R.) 423 (John Young Parkway) from south of Portage Street to north of Vine Street.        

Contact Information
Contractor
Masci General Contractor, Inc.
Communications Team
Peyton Reese
(321) 319-8130
Peyton.Reese@dot.state.fl.us