This project has been completed and is only available for historical reference.
Project Details
Work Type: Intersection Construction
Phase: Completed
Length: 1.099 miles
City:
County:
Road:
Construction Cost: $1.88 Million
Project Start: Early 2017
Est. Completion: Late 2017
About
This project consists of the construction of a second southbound left turn lane and a westbound right turn lane along with a new mast arm signal at the intersection of State Road (S.R.) 500 (U.S. 17/92) and U.S. 192 (Vine Street), and the construction of a northbound and a southbound right turn lane and re-loop the existing signalized intersection at the intersection of S.R. 500 (U.S. 17/92) and Donegan Avenue.
Contact Information
Contractor
Atlantic Civil Constructors Corporation
Communications Team
Peyton Reese
(321) 319-8130
Peyton.Reese@dot.state.fl.us