Work Type: Widening
Phase: Completed
Length: 1.042 miles
City:
County:
Road:
Construction Cost: $33.66 Million
Project Start: Fall 2017
Est. Completion: Fall 2020
About

The project includes reconstruction of State Road (S.R.) 46 into a six-lane divided urban roadway. This section would provide a 22-foot raised median, three travel lanes in each direction, buffered bike lanes, curb and gutter, and 5-foot sidewalks.

 