Orange County – Starting Sunday night, motorists need to be on the lookout for multiple lane closures along I-4—from from east of Conroy Road to east of Sand Lake Road—as the Florida Department of Transportation begins a resurfacing project on the westbound side of the interstate.



The cost is nearly $3 million dollars and lasts 170 days. The project limits, from east of Conroy Road to east of Sand Lake Road, cover about four (4) miles. Hubbard Construction is the contractor. Weather conditions could alter the schedule.

 

The planned lane closures are as follows:

•         August 12 (Sunday Night) – August 17 (Friday morning)
•         Work will occur from 9 p.m. to 5 a.m.
•         Traffic could be reduced to one lane during a portion of that time period.




The Florida Department of Transportation urges motorists to drive carefully in construction zones, and encourages all vehicle occupants to buckle up. Safety belts save lives.