•2/06/12- 2/08/12;7pm-6:30am
•US 27 & US 441 northbound and southbound lane closures
- No lane closures anticipated
•2/4/12-2/5/12; 7pm-8am
•US 27 Intermittent northbound lane closures
•2/5/12-2/11/12; 9pm-5am
•CR 464 Eastbound and westbound intermittent lane closures
- 02/05/12 - 02/10/12, Sunday - Friday
- 09:00 PM - 06:00 AM
- NB and SB lane closures on JYP to install new drainage, crossing JYP and OUC Electric.
•02/06/12 - 02/10/12, Monday - Friday
•10pm - 6am
•There will be intermittent lane closures in the north and southbound lanes of I-95.
•01/30/12 - 02/03/12, Monday - Friday
•10pm - 6am
•There will be intermittent ramp closures throughout the week nights.
- 02/06/12 - 02/11/12, Monday - Saturday
- SR 46 lanes EB and WB will be reduced down to one lane in each direction.
- 8:00 PM - 5:30 AM.
- There will also be intermittent complete road closures on SR 46 EB and WB between the EB and WB I-4 ramps.
- 12:00 AM - 5:00 AM
- This complete road cloure will be limited to a maximum of 20 minutes during this period to install Steel Bridge Girders on the I-4 Bridge over SR 46.
•Intermittent lane closures eastbound and westbound
- 02/05/12 - 02/11/12, Sunday - Saturday
- Project Completed
- No Lane Closures
7:ooam to 7:00pm, Sunday thru Saturday
Traffic will shift to the inside lane westbound from just east of Indian Lake Rd. to Kepler Rd. to plain the outside lane westbound. The speed limit has been reduced from Indian Lake Rd. to Clarks Bay Rd. to 55 mph.
•02/06/12 - 02/10/12, Monday - Friday
•8pm - 6am
•There will be intermittent lane closures on SR 520 for paving work.
7:00am to 7:00pm, Sunday thru Saturday
US-1 northbound right thru lane and right turn lane closed.
•02/06/12 -02/10/12, Monday - Friday
•7am - 5:30pm
•There will be intermittent lane closures in the northbound lanes for barrier wall placement and paving operations.
7:ooam to 7:00pm, Sunday thru Saturday
Traffic will shift to the inside lane westbound from just east of Indian Lake Rd. to Kepler Rd. to plain the outside lane westbound. The speed limit has been reduced from Indian Lake Rd. to Clarks Bay Rd. to 55 mph.
- 02/05/12 -02/11/12, Sunday - Saturday
- 8pm - 6am
- Nightly lane closures throughout project for layout and installation of curb and traffic separators.
- 02/05/12 - 02/11/12
- No anticipated lane closures.
- 02/05/12 - 02/11/12, Sunday - Saturday
- No anticipated lane closures.
- 02/05/12 - 02/11/12, Sunday - Saturday
- No anticipated lane closures.
- 02/05/12 - 02/11/12, Sunday - Saturday
- No anticipated lane closures
- 02/05/12 - 02/11/12, Sunday - Saturday
- No anticipated lane closures.
7:00am to 7:00pm, Sunday thru Saturday
Daytime lane closures (7:00am to 5:00pm) are expected along Seabreeze Blvd. in Daytona Beach. Also Monday through Thursday, nightime lane closures (9:00pm to 7:00am) are expected along Granada Blvd. in Ormond Beach,
- 02/05/12 - 02/11/12, Sunday - Saturday
- No anticipated lane closures.
•The I-75 Northside Weigh Station in Wildwood is closed
Please Wait...