EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Project Details
Work Type: Resurfacing
Phase: Construction
Length: 15.477 miles
City:
County:
Road:
Construction Cost: $14.4 Million
Project Start: Spring 2024
Est. Completion: Summer 2025
About

The purpose of this project is to repave State Road (S.R.) 11 from the Volusia County Line to south of County Road (C.R.) 304 and from north of C.R. 304 to U.S. 1 in Flagler County. A roundabout is being constructed at the intersection of S.R. 11 and C.R. 304 under project 439156-1.

Pedestrian safety improvements include widening the existing 4-foot-wide sidewalk to 6 feet wide where possible, installing three new mid-block crosswalks equipped with Rectangular Rapid Flashing Beacons (RRFBs), and constructing a shared-use trail along the east side of S.R. 11 between Old Haw Creek Road and Bay Street.

Two of the new mid-block crossings will be installed on S.R. 11 to the north and to the south of Main Street. These crossings will be slightly elevated to be level with the sidewalk, which enhances safety by making pedestrians more visible to motorists while crossing and encourages drivers to naturally slow down when approaching the crosswalk. The new mid-block crossing installed north of Pine Meadows Drive will not be raised.

Contact Information
Communications Team
Britney Jones
(386) 740-3566
Britney.Jones@dot.state.fl.us
Contractor
Masci General Contractor, Inc.
Lane Closures
  • Starting as early as May 7, all lanes of County Road (C.R.) 304 on the east side of the State Road (S.R.) 11 (Perkins Highway) intersection in the unincorporated community of Cody’s Corner, Flagler County, will close for up to six months. This closure is necessary to construct the first half of the roundabout at this intersection. A detour will be in place, and motorists will be directed around the roadway closure by signage.

    DETOUR:

    • Motorists traveling eastbound on C.R. 304 will be directed to turn left onto S.R. 11 and then right onto U.S. 1 to return to C.R. 304.
    • Motorists wishing to access C.R. 304 west of S.R. 11 will be directed to take U.S. 1 to S.R. 11 and head south to C.R. 304.

    Access to local roads and nearby properties, including Cody’s Corner General Store, will be maintained throughout construction.

    Please note that the construction schedule is subject to change pending weather or other unforeseen circumstances.

Goes With
Project Files